Colorado Boulevard's next round of transit planning will focus on crossings, sidewalks and smaller bus-service improvements while a broader bus rapid transit reassessment waits until 2028, under the Colorado Department of Transportation's revised approach.
In its November 4 update, CDOT said it would pursue targeted fixes first and remove center-running bus lanes from future consideration. The agency is asking residents which crossings and sidewalk stretches should receive priority.
The change separates work on reaching bus stops and crossing the road from the larger decision about how buses would move along the corridor. People walking, using wheelchairs or pushing strollers could benefit from individual safety projects as they are designed and funded. Riders seeking a continuous rapid-transit service face a longer planning process.
The funding starts later than the planning
CDOT says Colorado Boulevard has been prioritized for $21 million from its 10-Year Plan, with those funds budgeted to begin in fiscal 2031. The agency says that amount will be insufficient to complete all the safety and quality-of-life improvements it has identified.
Its approach is to move individual elements toward design so they can compete for other grants sooner. CDOT also intends to ask Denver's Sidewalk Enterprise Fund to prioritize the boulevard.
That puts project selection at the center of the next phase. A list of needed fixes has to become a sequence of funded designs and construction projects. The current announcement describes a proposed approach and funding strategy; individual delivery dates will depend on that work.
Which places CDOT has identified
The agency's update names Bruce Randolph Avenue, 6th and 7th avenues, Mississippi Avenue, 1st Avenue, Florida Avenue and 35th Avenue as intersections needing improvements.
It also identifies sidewalk deficiencies between East Martin Luther King Junior Boulevard and East 26th Avenue; between 6th Avenue and Bayaud Avenue; and on the east side between Warren Avenue and Wesley Avenue.
Those gaps matter for transit access. A bus stop across a difficult crossing, or beyond a sidewalk that a wheelchair cannot safely use, limits the usefulness of the service. CDOT says it will also work with Denver on signal timing and transit-priority opportunities to improve bus reliability.
The public feedback form lets residents rank intersection and sidewalk priorities and submit comments or questions. CDOT's update identifies prioritization as the purpose of this round of input.
The dispute over center-running lanes
CDOT says its initial study was sufficient to remove a center-running bus configuration from future review. It expects to begin reviewing other BRT options in 2028, informed by performance data from other corridors.
A coalition including Denver Streets Partnership, CoPIRG, SWEEP, Greater Denver Transit and the Colorado Cross Disability Coalition responded on November 9. The groups welcomed near-term sidewalk and crossing work but urged CDOT to retain all BRT design options until more operating data is available. They also called for a decision that would keep construction on track for 2031.
That 2031 construction goal is the advocates' request. CDOT's dated update places its identified $21 million allocation in fiscal 2031 and describes further funding and design work ahead. Those are different milestones for residents and businesses trying to plan around the project.
The evergreen project overview still describes a 2027 preliminary-design path. CDOT's November 4 announcement sets out the revised 2028 reassessment. For the current phase, residents can use the feedback form to identify the crossing or sidewalk that would most improve their daily trip.
Sources
- CDOT November 4 revised approach: https://www.codot.gov/news/2026/november2026news/accelerated-colorado-boulevard-improvements
- CDOT current priority feedback form: https://www.codot.gov/projects/studies/denvermetrobrt/coloradoblvd/feedback
- CDOT project overview, earlier schedule: https://www.codot.gov/projects/studies/denvermetrobrt/coloradoblvd
- Transit advocates' November 9 statement: https://denverstreetspartnership.org/project/press-release-transit-advocates-respond-to-cdots-delay-of-colorado-boulevard-bus-rapid-transit-brt-project/
- 9News November 10 reporting: https://www.9news.com/article/news/local/cdot-drops-center-bus-lanes-for-colorado-boulevard-leaving-both-sides-of-the-brt-fight-unhappy/73-d29d4746-025d-4406-a8f1-d55678f1e7ed
- Denver Gazette November 12 reporting, updated November 13: https://www.denvergazette.com/2026/11/12/cdot-pauses-full-colorado-boulevard-brt-review-until-2028/